On 26 September 2025, the Indian Air Force flew its last MiG-21s into retirement at Chandigarh, ending 62 years of service. The aircraft that was supposed to replace them had first flown almost 25 years earlier. That gap tells you most of what you need to know about the HAL Tejas: it is a real achievement, it is a genuinely capable little fighter, and it has spent its whole life running late.
This is the story of how India built the Tejas, what is actually inside it, how the production lines are doing, and why, as of early November 2026, not a single upgraded Tejas Mk1A has yet been formally handed to the Air Force.

A programme born in 1983
The Light Combat Aircraft (LCA) programme was approved by the Government of India in 1983. A year later, the Aeronautical Development Agency (ADA) was set up under the DRDO to run it, with Hindustan Aeronautics Limited (HAL) as the main industrial partner. The brief was ambitious for a country that had never designed a modern supersonic fighter: build a small, agile, multirole jet at home, and stop depending on foreign suppliers for the backbone of the fighter fleet.
India also tried to build the engine. The Gas Turbine Research Establishment began work on the Kaveri in 1986, but the engine never reached the thrust the aircraft needed. The stopgap was the American General Electric F404, and that “temporary” choice has quietly shaped the programme ever since. Every Tejas flying today runs on a GE engine.
Then came 1998. After the Pokhran-II nuclear tests, US sanctions ended Lockheed Martin’s help on the flight control system. ADA’s engineers ended up writing their own quadruplex digital fly-by-wire system. It cost roughly 18 months, but it also meant India now owned one of the hardest pieces of fighter technology outright.
First flight and a name
On 4 January 2001, Wing Commander Rajiv Kothiyal took Technology Demonstrator-1 (TD-1) up from Bengaluru for an 18-minute flight. In May 2003, Prime Minister Atal Bihari Vajpayee gave the LCA its name: Tejas, Sanskrit for “radiance”.
The road from first flight to a combat-ready jet was long. Initial Operational Clearance came in January 2011. Final Operational Clearance, the stamp that says the aircraft is fully cleared for its combat role, was formally handed over at Aero India on 20 February 2019. In between, No. 45 Squadron, the “Flying Daggers”, became the first Tejas unit in July 2016. It is now based at Sulur near Coimbatore. No. 18 Squadron, the “Flying Bullets”, followed on 27 May 2020.

What makes the Tejas tick
The Tejas is small. That isn’t a flaw; it’s the design. It uses a tailless compound delta wing and is built with “relaxed static stability”, which means the aircraft is deliberately a little unstable and relies on its computers to keep it flying straight. The payoff is agility. Around 45% of the airframe by weight, and about 90% of its surface area, is made of composites, which keeps it light and helps cut its radar signature.
| Specification | Tejas (Mk1 family) |
|---|---|
| Role | Single-engine, multirole light fighter |
| Length / wingspan / height | 13.2 m / 8.2 m / 4.4 m |
| Maximum take-off weight | About 13,500 kg |
| Engine | GE F404-IN20, roughly 84–85 kN with afterburner |
| Top speed | Mach 1.6 |
| Service ceiling | 15,240 m (50,000 ft) |
| G limits | +8 g / −3.5 g |
| Hardpoints | 8, plus an internal 23 mm GSh-23 twin-barrel cannon |
For weapons, the Tejas carries the Israeli Derby and India’s own Astra beyond-visual-range missiles, the Russian R-73 and Israeli Python-5 for close combat, laser-guided bombs and targeting pods. The ASRAAM short-range missile is planned for the Mk1A.
The Mk1A: same airframe, a lot more brain
The Mk1A is where the Tejas stops being a technology showcase and becomes a frontline fighter. The airframe looks almost identical, but the insides have changed. The biggest addition is an AESA radar: the early Mk1A batches use Israel’s Elta EL/M-2052, while later aircraft are meant to carry the Indian-developed Uttam. In July 2026, HAL placed a ₹2,205 crore order with Astra Microwave for Uttam radar hardware, which tells you that switch is now serious. The Mk1A also gets a new electronic warfare suite, air-to-air refuelling and a long list of maintainability fixes the IAF had asked for.

Production: the numbers behind the headlines
The Air Force’s first two Tejas Mk1 orders were modest: 20 aircraft in 2006 and another 20 in 2010. Even those took a long time to deliver, and the last two trainers ran years behind schedule.
The Mk1A orders are a different scale altogether:
- February 2021: 83 aircraft (73 fighters and 10 twin-seat trainers), worth about ₹48,000 crore. At the time it was HAL’s largest-ever fighter contract.
- 25 September 2025: 97 more aircraft (68 fighters and 29 twin-seaters) for ₹62,370 crore, excluding taxes, with over 64% indigenous content.
That brings the total to 180 Tejas Mk1As, worth roughly ₹1.1 lakh crore combined.
To build them, HAL now runs three Tejas lines. Two in Bengaluru can turn out about 16 aircraft a year between them. A third line at Nashik, set up for over ₹150 crore, adds eight more, which takes total capacity to 24 jets a year. Defence Minister Rajnath Singh opened the Nashik line on 17 October 2025 and watched the first Nashik-built Mk1A fly that same day.

So why hasn’t the IAF got its jets?
HAL was originally expected to start delivering the Mk1A around February–March 2024. More than two and a half years later, the first formal handover still hasn’t happened. There are two main reasons.
First, engines. HAL signed a ₹5,375 crore contract with GE in August 2021 for 99 F404-IN20 engines. GE’s supply chain struggled after the pandemic, and the first engine under that deal only arrived in March 2025, about two years late. By autumn 2026, HAL had received around 10 to 11 engines. A further contract for 113 engines, to power the second batch of 97 jets, was signed in November 2025.
Second, integration. Even with engines arriving, the jets need to be certified in the configuration the Air Force actually paid for. HAL chairman Ravi K has said 27 Mk1A airframes have been built. But the work of making the AESA radar talk properly to the weapons and the electronic warfare suite, and getting military airworthiness clearance from CEMILAC, has dragged on. Reports in October 2026 said only two or three radar-related issues were left. Ravi K said missile integration was done, though more test sorties were still needed.
The Air Force has made its frustration public. Former Air Chief Marshal A.P. Singh openly said the delays were hurting the IAF’s planning. His successor, Air Chief Marshal Ashutosh Dixit, has made the Tejas Mk1A and Mk2 his top priority, along with the AMCA. He has called restoring the IAF’s combat strength his “foremost task”. The numbers explain why. The IAF is down to about 30 fighter squadrons against a sanctioned strength of 42, and with the MiG-21 gone, that gap isn’t going to close by itself. It is also why the IAF is pursuing a separate 114-jet MRFA deal alongside the Tejas.
The latest signals are cautiously positive. In September 2026, Air Marshal Ashutosh Dixit, then Vice Chief of the Air Staff, said the first aircraft could be inducted within a month or two if the remaining technical points were proven. A HAL–IAF review was due after mid-October, and HAL is aiming for its first deliveries before the end of 2026, with around 10 aircraft in the 2026–27 financial year. For the second order of 97 jets, a defence ministry document puts deliveries between September 2027 and September 2033. In other words, the Tejas fleet will keep growing into the 2030s.
Two crashes in 25 years
For most of its life, the Tejas had a remarkable safety record. Its first crash came on 12 March 2024, near Jaisalmer in Rajasthan, more than 23 years after its first flight. The pilot ejected safely.
The second was far more painful. On 21 November 2025, a Tejas crashed during its flying display at the Dubai Airshow, killing Wing Commander Namansh Syal. The IAF ordered a court of inquiry. It was a hard moment for a programme that had gone to Dubai partly to win over foreign buyers.
The export question
Exports are the Tejas programme’s unfinished business. Its best chance so far was Malaysia, which in February 2023 chose South Korea’s KAI FA-50 instead for its order of 18 light combat jets. Several other air forces have shown interest over the years, but none has signed a contract. The honest problem is supply, not just competition. While HAL is still racing to deliver the IAF’s own 180 jets, it is hard to promise a foreign customer a firm delivery date.

What comes next: the Mk2 and beyond
The Tejas Mk2 is effectively a new, larger aircraft. It has canards, more internal fuel, a heavier payload and the more powerful GE F414-INS6 engine. Its timeline has slipped too: as of October 2026, reports say its first flight is now targeted for the third quarter of 2027. The naval version proved it could take off from and land on a carrier (INS Vikramaditya in 2020), but the Navy opted out back in 2016 and is now looking at the twin-engine TEDBF for its carriers. Beyond the Tejas family, India’s next big leap is the fifth-generation AMCA. We break down that programme in our AMCA explainer.
The verdict
It is easy to make fun of the Tejas for its delays, and many people do. But it helps to look at the whole picture. India started in 1983 with no modern fighter design experience. Today it has a supersonic multirole jet in squadron service, its own fly-by-wire system and composite airframe, three production lines, and an order book of 180 jets. Very few countries have done that. It is a different philosophy from Pakistan’s Chinese-backed JF-17 Thunder, and a very different class of jet from the heavyweights in our comparison of the world’s top fighter jets.
Still, in air power, timing matters as much as capability. The Mk1A’s success will be measured in the next 24 months. The question is not whether it can fly, because it clearly can. It’s whether HAL and GE can deliver jets fast enough to stop the IAF’s squadron numbers from shrinking further. If they manage it, the Tejas will finally be what it was always meant to be: the backbone of India’s fighter fleet, built at home.
Frequently asked questions about the HAL Tejas
What does “Tejas” mean?
Tejas is Sanskrit for “radiance”. Prime Minister Atal Bihari Vajpayee gave the Light Combat Aircraft its name in May 2003.
Who designs and builds the Tejas?
The Tejas was designed by the Aeronautical Development Agency (ADA) under India’s DRDO. It is built by Hindustan Aeronautics Limited (HAL) on lines in Bengaluru and Nashik.
What engine does the Tejas use?
The Tejas Mk1 and Mk1A use the American GE F404-IN20 turbofan. The larger Tejas Mk2 will use the more powerful GE F414-INS6.
How many Tejas Mk1A jets has India ordered?
India has ordered 180 in total: 83 in February 2021 and 97 more in September 2025. Together the two contracts are worth about ₹1.1 lakh crore.
Why is the Tejas Mk1A delayed?
There are two main reasons. GE delivered F404 engines about two years late. Integrating and certifying the AESA radar with the jet’s weapons and electronic warfare suite has also taken longer than planned.
How fast is the Tejas?
The Tejas has a top speed of about Mach 1.6 and a service ceiling of 50,000 feet (15,240 m).
Sources include the Ministry of Defence, Hindustan Aeronautics Limited, Akashvani News, The Week, Gulf News, Business Today, Defense News and IDRW. Figures are current as of 3 November 2026.